Concrete Calculator — How Much Concrete Do You Need?
Cubic yards, bags and cost — by slab, footing, wall, column, steps or post hole.
Slab, footing, wall, column, steps and post holes | 80, 60 and 40 lb bags | Ready-mix vs bagged | 2026 prices
Concrete Calculator
0.5–24 inches. Patios are usually 4 inches; driveways 4–6 inches.
45 × 80 lb, 60 × 60 lb or 90 × 40 lb bags per cubic yard.
Free — no sign-up.
Enter your measurements to see your result.
Quick answer: A 10 × 12 ft concrete slab, 4 inches deep, needs 1.48 cubic yards — order 1.63 cubic yards (74 × 80 lb bags) with the usual 10% waste allowance. Under 5 yards, a ready-mix plant adds a $50–$150 short-load fee.
How we check our math — reviewed November 9, 2026. Every formula is worked by hand against the US customary definition (National Institute of Standards and Technology) and manufacturer bag yields (Quikrete). Found a mistake? Tell us — we check every correction report and fix verified errors.
Rule of thumb: 45 × 80 lb bags, 60 × 60 lb bags, or 90 × 40 lb bags make one cubic yard. Do not work bags out from weight: a yard of concrete weighs about 4,050 lb, and 4,050 ÷ 80 = 51 bags — which is wrong, because bag yields are set by volume, not weight.
A 10 × 12 ft slab at 4 inches deep needs 1.48 cubic yards of concrete — order 1.63 cubic yards with the usual 10% waste allowance. That is 74 bags of 80 lb concrete mix, or a ready-mix load of $204–$318 plus a $50–$150 short-load fee. This concrete calculator works out yards, all three bag sizes, and ready-mix vs bagged cost, so you can decide whether to mix bags or call the truck.

Volume notice: Concrete is sold by volume, not weight. A cubic yard weighs about 2.03 tons (4,050 lb), but bags are fixed by yield — 0.60 cubic feet per 80 lb bag.
How the concrete calculator works
The formula is the same as for any volume: cubic yards = length × width × depth in feet, divided by 27. One cubic yard is 27 cubic feet, or 0.7646 cubic meters. A wall is length × height × thickness, a column is its circular area × height, and steps are a triangular prism — half of height × run × width. Use the concrete calculator above to check your own numbers.
Worked example — slab: A slab 10 ft long, 12 ft wide, 4 inches deep. Area: 10 × 12 = 120 sq ft. Cubic feet: 120 × (4 ÷ 12) = 40.0 ft³. Cubic yards: 40.0 ÷ 27 = 1.48 yd³. Order volume with 10% waste: 1.48 × 1.10 = 1.63 yd³ (44.0 ft³). Bags: 44.0 ÷ 0.60 = 73.3, rounded up to 74 × 80 lb bags (98 × 60 lb, or 147 × 40 lb). Cost: ready-mix 1.63 × $125–$195 = $204–$318, plus the $50–$150 short-load fee = $254–$468; bagged 1.63 × $270–$290 = $440–$473.
Worked example — post hole: A hole 12 inches across and 24 inches deep. Radius is 0.5 ft, so the area is π × 0.5² = 0.785 sq ft, and the volume is 0.785 × 2 ft = 1.57 ft³, which is 0.06 yd³. Bags: 1.57 ÷ 0.60 = 2.6, rounded up to 3 × 80 lb bags — and bags are rounded up per hole, so ten identical holes take 30 bags.
Bag or truck? The concrete decision
Under about 1 cubic yard — a few post holes, a small repair, a narrow path — bags usually win: no minimum load, no short-load fee, and you can work at your own pace. Above that, mixing dozens of bags by hand is slow work, and the concrete sets before you finish. A ready-mix truck delivers it all at once, already mixed, and for two yards or more it is usually cheaper per yard than bags. Plants usually charge a short-load fee under 5 cubic yards — $50–$150 flat on this site’s 2026 planning range, although some plants charge $40–$250 per yard short of their minimum.
- Ready-mix: $125–$195 per cubic yard.
- Bagged concrete: $270–$290 per cubic yard, all-in.
- Short-load fee: $50–$150 flat under 5 cubic yards.
- Delivery: $50–$150 per trip, only when you tick it in the calculator.
Those are 2026 planning ranges, not a quote. Prices move by region, by season, and by how far the truck has to drive.
Depth by project
| Project | Depth |
|---|---|
| Patio or walkway slab | 4 in |
| Driveway slab | 4–6 in |
| Garage floor | 4–6 in |
| Footing | 8–12 in |
| Wall | 6–12 in thick |
| Post hole | 24–36 in deep |
Coverage per cubic yard by depth
| Depth (inches) | Sq ft per yard |
|---|---|
| 1 | 324 |
| 2 | 162 |
| 3 | 108 |
| 4 | 81 |
| 6 | 54 |
| 8 | 41 |
Bags per cubic yard
| Bag size | Yield per bag | Bags per cubic yard |
|---|---|---|
| 80 lb | 0.60 ft³ | 45 |
| 60 lb | 0.45 ft³ | 60 |
| 40 lb | 0.30 ft³ | 90 |
Waste allowance by project type
| Project type | Extra to order |
|---|---|
| Flat slab, patio | +10% |
| Driveway, base | +10% |
| Footings and walls | +10% |
| Post holes | +10% (round up per hole) |
| Sloped or rough ground | +10–15% |
| First time ordering | +10% |
Texas note
In West Texas, pour early in the day — the heat dries fresh concrete fast, and a slab poured at noon in July can set before you have finished it. The ground under your project is often caliche, so shape and compact the subgrade carefully; a slab is only as flat as what it sits on. Put control joints in every 8–12 feet.
Frequently asked questions
How many 80 lb bags of concrete are in a cubic yard?
45. An 80 lb bag yields 0.60 cubic feet, and a cubic yard is 27 cubic feet, so 27 ÷ 0.60 = 45 bags. The same yard takes 60 × 60 lb bags or 90 × 40 lb bags.
Why do some concrete calculators give the wrong bag count?
They divide the weight of a yard (about 4,050 lb) by the bag weight — 4,050 ÷ 80 = 51 bags — but bags are sold by volume yield, not by weight. The manufacturer’s yield for an 80 lb bag is 0.60 cubic feet, which gives 45 bags per yard.
How much concrete do I need for a 10 × 10 ft slab, 4 inches deep?
1.23 cubic yards measured (100 sq ft × 4 ÷ 324), and 1.35 cubic yards to order with 10% waste — 61 × 80 lb bags. That is under the usual 5-yard ready-mix minimum, so expect a $50–$150 short-load fee.
What is a short-load fee?
It is the fee a ready-mix plant charges for a load under its minimum, usually 5 cubic yards. On this site’s 2026 planning range it is $50–$150 flat, although some plants charge $40–$250 per yard short of the minimum.
Should I use bags or a ready-mix truck?
Bags suit jobs under about 1 cubic yard — post holes, repairs, small paths. Above that, a truck is usually cheaper per yard and far faster, and you avoid the risk of the first bags setting before the last are mixed.
Can you pour concrete in cold weather?
Yes — with protection. The American Concrete Institute (ACI 306) treats it as cold-weather concreting when the air temperature is at or below 40°F during the protection period. For a normal patio or driveway slab (under 12 inches thick), the concrete should be placed and kept at 55°F or above, and it must not freeze before it reaches about 500 psi — roughly the first 24 to 48 hours. In practice that means pouring midday, making sure the ground underneath is not frozen, and covering the slab with insulating blankets overnight if a freeze is forecast. In Lubbock, November daytime highs are usually in the 60s, so a November pour is normally fine — just check the overnight forecast before you book the truck.
Related tools
Try the Cubic Yard Calculator for any material by volume, the Gravel Calculator for driveway bases in yards and tons, and the Sand Calculator for paver bedding and concrete sand.
Sources and methodology: The 27 cubic feet in a cubic yard is the US customary definition (National Institute of Standards and Technology). Bag yields of 0.60, 0.45 and 0.30 cubic feet for 80, 60 and 40 lb bags are the manufacturer’s published yields (Quikrete). Ready-mix and bagged concrete price bands are 2026 US planning ranges.
Calculation notice: Results are estimates for planning and ordering. Actual volume depends on how the subgrade is shaped, spillage, and the mix used. All prices are 2026 planning ranges, not a quote.